ROADWAY IMPROVEMENTS - WORK UPDATES

KINGS HIGHWAY PROJECT UPDATE
 
KINGS HIGHWAY PROJECT
 
Dedicated website for updates from Camden County - CLICK HERE
 

Below please find the projects scheduled during the week of November 25, 2024.

Monday November 25 thru Wednesday November 27, 2024

  • West Nicholson Road – 7:00am to 5:30pm. Roman E&G, on behalf of PSE&G Electric, will continue the concrete restoration, there will be a full road closure between Brittin Avenue & Central Avenue.

 

Monday November 25 thru Wednesday November 27, 2024

  • Kings Highway – 7:00am to 5:00pm.  South State, on behalf of Camden County, will continue the sanitary sewer main and lateral replacements and Capital Concrete will be replacing curbs, sidewalks, driveways between West Atlantic Avenue & East Lake Road using a full road closure on the Haddon Height side of the road and two-way traffic on the Audubon side of the road. 

 

 

 

Below please find the projects scheduled for your town during the week of 11/18:

 Monday November 18 thru Friday November 22, 2024

  • Kings Highway – 7:00am to 3:30pm.  South State, on behalf of Camden County, will continue the sanitary sewer main and lateral replacements and Capital Concrete will be replacing curbs, sidewalks, driveways between West Atlantic Avenue and East Lake Road using a full road closure.  Also, South State will be performing drainage work between 3rd Avenue & 4th Avenue using a shoulder/sidewalk closure.

 

Thursday November 21 & Friday November 22, 2024

  • West Nicholson Road – 7:00am to 5:30pm. Roman E&G, on behalf of PSE&G Electric, will continue the concrete restoration, there will be a full road closure between Brittin Avenue & Central Avenue.

 

 

 

 

 

CONSTRUCTION PROJECTS FOR THE WEEK OF NOVEMBER 11, 2024

Below please find the project scheduled for your town during the week of 11/11:

 Monday November 11 thru Friday November 15, 2024

  • Kings Highway – 7:00am to 3:30pm.  South State, on behalf of Camden County, will continue the sanitary sewer main and lateral replacements between West Atlantic Avenue and East Lake Road using a shoulder/lane closure.  Also, Capital Concrete, working under South State and on behalf of Camden County, will continue the concrete work using alternating traffic with flaggers between Black Horse Pike and East Lake Drive on Monday-Wednesday and South State will pave this segment on Thursday & Friday.  Finally, South State will be performing drainage work between West Atlantic Avenue & Hopkins Road using a shoulder/sidewalk closure.

 

In addition to the above, if there are any projects on County roads that you are aware of and do not see listed, please let me know. All contractors are required per the County permit regulations to provide notice of the work being done on a County roadway and need to file the proper permit.

 

Please call with any questions.  Thank you.

 

Please be advised that Kings Highway between Black Horse Pike (NJ-168) and East Lake Drive will be paved next Thursday, 11/14 and Friday, 11/15, weather permitting. Working hours will be 7:00 AM to 3:30 PM.

During work, there will be a one-way detour in place. All Northbound thru traffic (i.e. traveling from Mt Ephraim to Audubon/Haddon Heights) will be detoured around the work zone. Detour signage will be posted directing traffic to turn left at Black Horse Pike and right on Merchant Street/Hampshire Avenue. Police will be onsite for assistance. All Southbound traffic (i.e. traveling from Audubon/Haddon Heights to Mt Ephraim) will be maintained.  A sketch is attached for your reference.

 

Access for residents, emergency vehicles, and local traffic will be maintained.

 
 
 
 
 
 

Below please find the projects scheduled for your town during the week of 11/4:

 

Monday November 4, 2024

  • West Nicholson Road – 8:30am to 4:00pm. PSE&G will be repairing a gas leak, there will be a lane shift between the Black Horse Pike & Road B. 

 Monday November 4 and Wednesday November 6 thru Friday November 8, 2024

  • Kings Highway – 7:00am to 3:30pm.  South State, on behalf of Camden County, will continue the sanitary sewer main and lateral replacements between West Atlantic Avenue and East Lake Road.  There will be lane and shoulder closures at the immediate work location(s).  Also, Capital Concrete, working under South State and on behalf of Camden County, will continue the curb, sidewalks, ADA ramp, and driveway apron installations between Black Horse Pike and East Lake Drive. There will be lane and shoulder closures at the immediate work location(s).

 Wednesday November 6, 2024

  • West Nicholson Road – 8:30am to 2:30pm. Verizon will be transferring and removing utility poles, there will be a shoulder closure between Cedarcroft Avenue & Central Avenue. 

 Thursday November 7 & Friday November 8, 2024

  • West Nicholson Road – 7:00am to 5:30pm. Roman E&G & Carroccia Contractors, on behalf of PSE&G Electric, will be installing sidewalks, curbing and driveways, there will be a full road closure between Brittin Avenue & Central Avenue.
 
 
 
 
 

Below please find the projects scheduled for your town during the week of 10/28:

Please be advised that there has been a change to the below plan for this week’s work. Rather than close Kings Highway entirely between Black Horse Pike and East Lake Drive, there will be a one-way detour in place.

All Northbound thru traffic (i.e. traveling from Mt Ephraim to Audubon/Haddon Heights) will be detoured around the work zone. Detour signage will be posted directing traffic to turn left at Black Horse Pike and right on Merchant Street/Hampshire Avenue. Police will be onsite for assistance. A sketch is attached for your reference.

All Southbound traffic (i.e. traveling from Audubon/Haddon Heights to Mt Ephraim) will be maintained.

The timing and scope of this work are unchanged; 7:00 AM, Wed. Oct. 30, 2024, until 3:00 PM, Thurs. Oct. 31, 2024. South State, Inc. will be removing and replacing some of the concrete roadway slabs which require 24 hours of curing time.

Access for residents, emergency vehicles, and local traffic will be maintained.